TEMPORARY TRAFFIC SIGNALS OUTSIDE 96 OLDHAM ROAD, SHAW

It is necessary to provide a new clean water service connection at 96 Oldham Road, Shaw. The work will commence on Tuesday 31 July and should take 2 days to complete. The road crossing will be undertaken in two halves with the trench back filled and reinstated at the end of each day.
 
The signals will operate off peak only (9.30am – 3.30pm)