Latest on getting Dunwood Park Tennis Courts and MUGA operational again

Dunwood park Tennis courts

As many people will be aware these works have not been completed in the timescale planned.  I and other local councillors have been working behind the scenes to get this area usuable by our young people.

Undocumented services and drains under the area that had to be dealt with have led to the delay.

I am pleased to now report we have got a solution that gets them open for this weekend but will require a closure later in the year to correctly finish the works, details below.

The new Box culvert has now been installed and the old tennis courts surface removed and replaced with a new Binder /surface to specification for applications of multi – use Games areas (MUGAs)

The reinstatement to the boundary wall is continuing this week and will be completed by Friday 28/07/2017.

The painting and lining markings in accordance with ( LTA standard Courts) should not be completed until 6-8 weeks after the new surface has been laid, to allow the gases and fats from the bitumen to disperse and ensure good adhesion of the paint.

As an interim measure the courts will be marked out on Thursday 27th July 2017 (Weather permitting), these line will be sacrificial and re-painted after the school holidays and the 6-8 weeks have expired.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.