Traffic signals Mosshey Street, Greenfield Lane and Refuge Street – works start 15 February and end 9 April

The Council have received a permit application to supply electricity and gas to a new development at Mosshey Street, Shaw

S&R Construction Ltd have obtained permission to undertake essential Multi Utility Works (Gas, Water & Electric) which will impact the roads referenced above.

Please refer to the below work phases, detailing start dates and durations, along with Traffic Management implementations.

Phase 1 – Mosshey Street– 15.02.2021-26.02.2021 / (duration 10 days)

  • Their works will involve excavation in the Footway from No. 27 Mosshey Street, towards the junction of Asda’s entrance. There will be no parking cones in place throughout the duration of our works to avoid vehicles blocking access to our working area.

Phase 2 – Greenfield Lane –01.03.2021-12.03.2021 (duration 10 days)

  • The works will involve excavation in the carriageway between the junction of Asda’s entrance, to the junction of Eastway. The works will be carried out under temporary two-way traffic signals.

Phase 3 –  Greenfield Lane – 15.03.2021-26.03.2021 (duration 10 days)

  • The works will involve excavation in the carriageway between the junction of Eastway, towards Refuge Street. The works will be carried out under temporary three-way signals.

Phase 4 –Refuge Street/Greenfield Lane- 29.03.2021- 02.04.2021 (duration 10 days)

  • The works will involve excavation in the footway and carriageway on Refuge Street where we will need to cross the width of the carriageway. These works will be carried out under four-way temporary traffic signals.

Phase 5 – Mosshey Street – 05.04.2021 – 09.04.2021 (duration 5 days)

  • The works will involve excavation in the footway of Mosshey Street. There will be no parking cones in place throughout the duration of our works to avoid vehicles blocking access to our working area.

They apologise for any inconvenience our works may cause you.

It is their intention to complete the works as quickly as possible to keep any disruption to a minimum. 

If you have any questions regarding the above, please do not hesitate to contact them:

Alysia Totney, Multi Utility Project Coordinator, S&R Construction Ltd, 01384 598103